AI TrendsNov 23, 2026 · 4 min read · QAI Lab

Three AI campuses still on paper face courts and permits

What changed on Global Infra: two projects leave the announced list, three still waiting face courts and reviews, and two Huawei campuses grow.

An announced AI data center is a power plan, a piece of land and a press release. Turning it into a building takes approvals for all three, and this week's changes on Global Infra show where projects stop or move.

Projects on the announced list19 → 17Khazna and Eni near Milan and Nanto Campus in Japan no longer show as announced, on thin evidence that either has started
Planned power of the projects still announced20.9 GW → 17.3 GWSum of the planned figures on the list (derived); some are press estimates
Huawei Wuhu, planned power526 MW → 589 MWBy December 2027, about 256 MW running now (Epoch AI estimate, Nov 21 2026)
Huawei Horinger, planned power414.6 MW → 438.8 MWBy February 2028, about 212 MW running now (Epoch AI estimate, Nov 21 2026)

Three projects still waiting face courts, reviews and regulators

Three projects on the announced list, in Canada, the US and Australia, still have an open approval step that the latest reports name: a court case, an environmental review or a regulator filing.

Wonder Valley in Alberta, backed by Kevin O'Leary, plans a 1.4 GW off-grid power system first, according to Alberta's major projects list, in the company's 7.5 GW plan. The company says power construction could start in 2027, after it files with the regulator by the end of this year, and the Sturgeon Lake Cree Nation has filed three judicial reviews against the project, BNN Bloomberg reported on November 3.

Project Sail, a nine-building campus on about 830 acres in Coweta County, Georgia that Propmodo reports Prologis is developing, won its rezoning by a 3 to 2 county vote in April; residents sued in May to void it, CBS News Atlanta reported. The 900 MW often quoted for it is a press estimate, not a Prologis figure.

NEXTDC's S7 campus at Eastern Creek in Sydney, planned at up to 612 MW in planning documents and the subject of a memorandum of understanding with OpenAI, is still at the stage of preparing its environmental impact statement on the New South Wales planning portal. Its first phase is targeted for the second half of 2027 if approved, The Urban Developer reported.

Reliance's plan in Andhra Pradesh, which the state government backs, is further along. The state's investment committee approved it in April, and a government order of May 20 allotted about 855 acres. Reliance plans 500 MW at Polipalli by October 2028, then 1 GW more at Bhogapuram by 2030, Business Today reported.

ProjectPlanned powerWhat it is waiting onSource
Wonder Valley, Alberta (O'Leary Digital)1.4 GW first, in a plan for 7.5 GWA regulator filing due by the end of 2026; three judicial reviews by the Sturgeon Lake Cree NationBNN Bloomberg, Nov 3 2026; Alberta major projects list
Project Sail, Coweta County, Georgia (Prologis)900 MW, a press estimateA residents' lawsuit to void the April 2026 rezoningPropmodo; CBS News Atlanta
S7, Eastern Creek, Sydney (NEXTDC)Up to 612 MWIts environmental impact statement, still being prepared; first phase in the second half of 2027 if approvedNew South Wales planning portal; The Urban Developer
Polipalli and Bhogapuram, Andhra Pradesh (Reliance)500 MW by Oct 2028, then 1 GW more by 2030Approved by the state investment committee in April 2026; about 855 acres allotted on May 20Business Today; the state order of May 20

Our call: at least two of Wonder Valley, Project Sail and NEXTDC S7 have not started construction on June 30, 2027. We are wrong if two or more of them start building by then. Confidence: medium.

Two projects left the announced list, on thin evidence

Our map no longer shows two projects as announced, and the evidence that either has started is thin. Khazna Data Centers and Eni plan up to 500 MW at Ferrera Erbognone, near Milan, powered by a new Eni gas plant with carbon capture. An Eni-sponsored article of September 22, 2025 said preliminary demolition on the former industrial site had begun, with the first stone planned for 2026, and Il Sole 24 Ore reported on August 10, 2026 that the European Union had cleared the joint venture while the campus was still being designed.

GigaStream Toyama's Nanto Campus in Japan plans 3.1 GW when complete, with a first phase of about 400 MW, according to its December 2025 announcement. Construction was scheduled to begin in spring 2026, with operations targeted for late 2028, according to a data-center listing on Baxtel. The spring start has passed and we found no report of a delay, but we found no report of construction either. If a source shows either project has not started, it goes back on the list.

Neither campus appears yet in the satellite-tracked layer of the map, which counts sites being built or running, so both leave the map until one does.

Two Huawei campuses in China are larger than first estimated

Epoch AI, whose estimates from satellite images, permits and public documents feed the map's layer of campuses being built or running, raised the planned power of the two Huawei campuses in China on the map. Huawei Wuhu is now planned at 589 MW by December 2027, up from 526 MW, with about 256 MW running. Huawei Horinger is planned at 438.8 MW by February 2028, up from 414.6 MW, with about 212 MW running. Both are less than half built on those estimates.

Huawei's two campuses in China are less than half built
Power, MW, Epoch AI estimates as of Nov 21 2026
Running nowPlanned
Huawei WuhuPlanned by Dec 2027; was 526 MW
256.0 MW
589.0 MW
Huawei HoringerPlanned by Feb 2028; was 414.6 MW
212.4 MW
438.8 MW
Source: Epoch AI, AI data centers (CC BY 4.0), estimates from satellite images, permits and public documents, as of Nov 21 2026.
Show as table
Running now, MWPlanned, MWDifference
Huawei Wuhu256.0589.0Planned by Dec 2027; was 526 MW
Huawei Horinger212.4438.8Planned by Feb 2028; was 414.6 MW

They are two of the three Chinese campuses with the most power running now, out of five on the map that together plan about 2.6 GW. The 77 US campuses on the map plan about 43.4 GW of the 50.4 GW across all 96.

Our calls, in one place

We grade every call when its date arrives, and the wrong ones stay up with their outcome.

Our callByWe are wrong ifConfidence
At least two of Wonder Valley, Project Sail and NEXTDC S7 have not started constructionJun 30 2027Two or more of them start building by thenMedium

Open Global Infra to see each campus on the map.

Not financial advice. Calls are QAI research views, not recommendations or solicitations. Conflicts of interest: none.