Three AI campuses still on paper face courts and permits
What changed on Global Infra: two projects leave the announced list, three still waiting face courts and reviews, and two Huawei campuses grow.
An announced AI data center is a power plan, a piece of land and a press release. Turning it into a building takes approvals for all three, and this week's changes on Global Infra show where projects stop or move.
Three projects still waiting face courts, reviews and regulators
Three projects on the announced list, in Canada, the US and Australia, still have an open approval step that the latest reports name: a court case, an environmental review or a regulator filing.
Wonder Valley in Alberta, backed by Kevin O'Leary, plans a 1.4 GW off-grid power system first, according to Alberta's major projects list, in the company's 7.5 GW plan. The company says power construction could start in 2027, after it files with the regulator by the end of this year, and the Sturgeon Lake Cree Nation has filed three judicial reviews against the project, BNN Bloomberg reported on November 3.
Project Sail, a nine-building campus on about 830 acres in Coweta County, Georgia that Propmodo reports Prologis is developing, won its rezoning by a 3 to 2 county vote in April; residents sued in May to void it, CBS News Atlanta reported. The 900 MW often quoted for it is a press estimate, not a Prologis figure.
NEXTDC's S7 campus at Eastern Creek in Sydney, planned at up to 612 MW in planning documents and the subject of a memorandum of understanding with OpenAI, is still at the stage of preparing its environmental impact statement on the New South Wales planning portal. Its first phase is targeted for the second half of 2027 if approved, The Urban Developer reported.
Reliance's plan in Andhra Pradesh, which the state government backs, is further along. The state's investment committee approved it in April, and a government order of May 20 allotted about 855 acres. Reliance plans 500 MW at Polipalli by October 2028, then 1 GW more at Bhogapuram by 2030, Business Today reported.
| Project | Planned power | What it is waiting on | Source |
|---|---|---|---|
| Wonder Valley, Alberta (O'Leary Digital) | 1.4 GW first, in a plan for 7.5 GW | A regulator filing due by the end of 2026; three judicial reviews by the Sturgeon Lake Cree Nation | BNN Bloomberg, Nov 3 2026; Alberta major projects list |
| Project Sail, Coweta County, Georgia (Prologis) | 900 MW, a press estimate | A residents' lawsuit to void the April 2026 rezoning | Propmodo; CBS News Atlanta |
| S7, Eastern Creek, Sydney (NEXTDC) | Up to 612 MW | Its environmental impact statement, still being prepared; first phase in the second half of 2027 if approved | New South Wales planning portal; The Urban Developer |
| Polipalli and Bhogapuram, Andhra Pradesh (Reliance) | 500 MW by Oct 2028, then 1 GW more by 2030 | Approved by the state investment committee in April 2026; about 855 acres allotted on May 20 | Business Today; the state order of May 20 |
Our call: at least two of Wonder Valley, Project Sail and NEXTDC S7 have not started construction on June 30, 2027. We are wrong if two or more of them start building by then. Confidence: medium.
Two projects left the announced list, on thin evidence
Our map no longer shows two projects as announced, and the evidence that either has started is thin. Khazna Data Centers and Eni plan up to 500 MW at Ferrera Erbognone, near Milan, powered by a new Eni gas plant with carbon capture. An Eni-sponsored article of September 22, 2025 said preliminary demolition on the former industrial site had begun, with the first stone planned for 2026, and Il Sole 24 Ore reported on August 10, 2026 that the European Union had cleared the joint venture while the campus was still being designed.
GigaStream Toyama's Nanto Campus in Japan plans 3.1 GW when complete, with a first phase of about 400 MW, according to its December 2025 announcement. Construction was scheduled to begin in spring 2026, with operations targeted for late 2028, according to a data-center listing on Baxtel. The spring start has passed and we found no report of a delay, but we found no report of construction either. If a source shows either project has not started, it goes back on the list.
Neither campus appears yet in the satellite-tracked layer of the map, which counts sites being built or running, so both leave the map until one does.
Two Huawei campuses in China are larger than first estimated
Epoch AI, whose estimates from satellite images, permits and public documents feed the map's layer of campuses being built or running, raised the planned power of the two Huawei campuses in China on the map. Huawei Wuhu is now planned at 589 MW by December 2027, up from 526 MW, with about 256 MW running. Huawei Horinger is planned at 438.8 MW by February 2028, up from 414.6 MW, with about 212 MW running. Both are less than half built on those estimates.
Show as table
| Running now, MW | Planned, MW | Difference | |
|---|---|---|---|
| Huawei Wuhu | 256.0 | 589.0 | Planned by Dec 2027; was 526 MW |
| Huawei Horinger | 212.4 | 438.8 | Planned by Feb 2028; was 414.6 MW |
They are two of the three Chinese campuses with the most power running now, out of five on the map that together plan about 2.6 GW. The 77 US campuses on the map plan about 43.4 GW of the 50.4 GW across all 96.
Our calls, in one place
We grade every call when its date arrives, and the wrong ones stay up with their outcome.
| Our call | By | We are wrong if | Confidence |
|---|---|---|---|
| At least two of Wonder Valley, Project Sail and NEXTDC S7 have not started construction | Jun 30 2027 | Two or more of them start building by then | Medium |
Open Global Infra to see each campus on the map.