Global Infra — The Infrastructure Map
The physical layer behind AI: AI data centers and the power they will need, plus the world's power lines, substations and plants, with data points on energy, critical minerals, trade and the environment.
AI data centers
Planned and under construction: the compute being built, and the power it will need
Coming online
GW of power at the end of each year, across the sites being tracked
What this shows: 50.3 GW planned, up from 19.4 GW drawing power today, as sites under construction are finished. Another 20.9 GW across 19 announced projects shows no sign of construction yet.
- 2021: 57 MW
- 2022: 82 MW
- 2023: 509 MW
- 2024: 2.5 GW
- 2025: 8.6 GW
- 2026: 22 GW
- 2027: 32.5 GW
- 2028: 49.9 GW
- 2029: 50.1 GW
- 2030: 50.3 GW
The largest sites
Planned GW of power, coloured by status
Click a site to see it on the map.
Announced projects
Stated power, checked 5 Nov 2026
What this shows: Plans with no sign of construction yet, so they stay out of every figure above.
| What’s stated | On the map | |||
|---|---|---|---|---|
| Nanto CampusGigaStream Toyama · Japan3.1 GW when complete. The first phase, about 400 MW, targets operations in 2028. The city said building could begin from spring 2026. Source | 3.1 GW | — | 3.1 GW when complete. The first phase, about 400 MW, targets operations in 2028. The city said building could begin from spring 2026. Source | |
| GS Donghae AI Data CenterGS Group · South Korea1.2 GW by 2028, then 1.2 GW more by 2029. The first 100 MW building got its permit in October 2026, and the developer plans to break ground this year. Source | 2.4 GWTarget 2029 | 2029 | 1.2 GW by 2028, then 1.2 GW more by 2029. The first 100 MW building got its permit in October 2026, and the developer plans to break ground this year. Source | |
| Paducah AI campusBrookfield · United StatesOn a former uranium enrichment site owned by the US government, with gas and batteries from NextEra. The power deal needs Kentucky regulators' approval, and no tenant is named. Source | 1.8 GWTarget 2031 | 2031 | On a former uranium enrichment site owned by the US government, with gas and batteries from NextEra. The power deal needs Kentucky regulators' approval, and no tenant is named. Source | |
| Reliance Bhogapuram AI clusterReliance Industries · India500 MW at Polipalli by October 2028, then 1 GW more at Bhogapuram by 2030. Andhra Pradesh's investment board cleared the plan in May 2026. Source | 1.5 GWTarget 2030 | 2030 | 500 MW at Polipalli by October 2028, then 1 GW more at Bhogapuram by 2030. Andhra Pradesh's investment board cleared the plan in May 2026. Source | |
| Wonder Valley AlbertaO'Leary Digital · CanadaA first phase of 1.4 GW of off-grid generation, in a plan for 7.5 GW in all. Still in permitting as of early 2026. Source | 1.4 GW | — | A first phase of 1.4 GW of off-grid generation, in a plan for 7.5 GW in all. Still in permitting as of early 2026. Source | |
| Stratos (Wonder Valley Utah)O'Leary Digital · United StatesCut from 9 GW after local backlash, with applications limited to a 1 GW first phase. An October 2026 filing still describes 7.5 GW of generation in time. A referendum effort and lawsuits are pending. Source | 1 GW | — | Cut from 9 GW after local backlash, with applications limited to a 1 GW first phase. An October 2026 filing still describes 7.5 GW of generation in time. A referendum effort and lawsuits are pending. Source | |
| Elsham Tech ParkElsham Tech Park Ltd (Greystoke) · United KingdomUp to 15 buildings and up to 1 GW. Outline permission came in March 2026, with detailed plans still needed. Building is expected from 2027 and the first phase in 2029. Source | 1 GW | — | Up to 15 buildings and up to 1 GW. Outline permission came in March 2026, with detailed plans still needed. Building is expected from 2027 and the first phase in 2029. Source | |
| Pantheon AI, TopuskoPantheon Atlas · Croatia1 GW in total, 800 MW of it for computing. Construction is scheduled for 2027 and operations for early 2029. The grid operator has accepted the connection study. Source | 1 GWTarget 2029 | 2029 | 1 GW in total, 800 MW of it for computing. Construction is scheduled for 2027 and operations for early 2029. The grid operator has accepted the connection study. Source | |
| E-Valley CambraiData4 (Brookfield) · FranceUp to 1 GW over time, about 300 MW first, with first deliveries expected in 2027 to 2028. In June 2026 the state said works were planned for the second half of 2026. Source | 1 GW | — | Up to 1 GW over time, about 300 MW first, with first deliveries expected in 2027 to 2028. In June 2026 the state said works were planned for the second half of 2026. Source | |
| Le Bosquel AI campusSoftBank Group and Sesterce · FranceA SoftBank and Sesterce joint venture, in a 3.1 GW first phase across three northern French sites due by 2031. No building schedule given. Source | 1 GWTarget 2031 | 2031 | A SoftBank and Sesterce joint venture, in a 3.1 GW first phase across three northern French sites due by 2031. No building schedule given. Source |
See all 19 announced projects
A free account shows every project with its owner, target date and source.
Numbers come from developers or press reports and often change. A selection, not every plan.
Every site
Estimated power and compute today and at full build, as of 5 Nov 2026, with the map showing the same set. Announced figures come from developers or press reports.
| Status | On the map | ||||
|---|---|---|---|---|---|
| Nanto CampusGigaStream Toyama · Japan | Announced | 3.1 GW | — | — | |
| Microsoft Fairwater WisconsinMicrosoft · United States | Expanding | 442 MW → 2.7 GW | 446K → 4.5M | 13 May 2028 | |
| OpenAI Stargate New MexicoOracle · United States | Under construction | 0 MW → 2.5 GW | 0 → 5.1M | 31 Dec 2028 | |
| GS Donghae AI Data CenterGS Group · South Korea | Announced | 2.4 GW | — | 2029 | |
| Anthropic-Amazon New CarlisleAmazon · United States | Expanding | 1.2 GW → 2.3 GW | 818K → 1.7M | 17 Mar 2028 | |
| Meta HyperionMeta · United States | Under construction | 0 MW → 2.2 GW | 0 → 4.1M | 1 Jan 2028 | |
| Colossus 2SpaceXAI · United States | Expanding | 1.3 GW → 2.1 GW | 1.1M → 1.8M | 25 Feb 2027 | |
| OpenAI Stargate ShackelfordOracle · United States | Under construction | 0 MW → 2 GW | 0 → 4.6M | 11 Nov 2028 | |
| Paducah AI campusBrookfield · United States | Announced | 1.8 GW | — | 2031 | |
| QTS Cedar RapidsMeta (speculative) · United States | Under construction | 0 MW → 1.6 GW | 0 → 2.3M | 15 Nov 2027 | |
| Reliance Bhogapuram AI clusterReliance Industries · India | Announced | 1.5 GW | — | 2030 | |
| OpenAI Stargate UAEG42 (likely) · United Arab Emirates | Under construction | 0 MW → 1.4 GW | 0 → 2M | 1 Jan 2028 | |
| Wonder Valley AlbertaO'Leary Digital · Canada | Announced | 1.4 GW | — | — | |
| OpenAI Stargate MichiganOracle · United States | Under construction | 0 MW → 1.4 GW | 0 → 2.9M | 31 Dec 2028 | |
| Meta PrometheusMeta · United States | Expanding | 612 MW → 1.3 GW | 536K → 1.2M | 1 Jul 2028 | |
| Stratos (Wonder Valley Utah)O'Leary Digital · United States | Announced | 1 GW | — | — | |
| Elsham Tech ParkElsham Tech Park Ltd (Greystoke) · United Kingdom | Announced | 1 GW | — | — | |
| Pantheon AI, TopuskoPantheon Atlas · Croatia | Announced | 1 GW | — | 2029 | |
| E-Valley CambraiData4 (Brookfield) · France | Announced | 1 GW | — | — | |
| Le Bosquel AI campusSoftBank Group and Sesterce · France | Announced | 1 GW | — | 2031 |
See all 72 sites
A free account shows every site with its owner, customers, build dates and sources, and lets you search and sort them.
The power grid
Lines and substations by voltage, as mapped
By voltage
Thousand km of line, by voltage
What this shows: 42% of mapped line runs at 200 kV and up, the long-distance backbone.
Click a band to show only those lines on the map. Street-level cables are left out.
Power plants
Recorded output by source, and the largest plants
By source
GW of recorded output, by source
What this shows: coal, gas and oil plants hold 66% of the recorded output.
Click a source to list its plants and show only them on the map. Many plants record no output, and a few record peak or planned output.
The largest plants
The 10 largest by recorded output
| On the map | ||||
|---|---|---|---|---|
| Three Gorges Dam | 22,500 | — | ||
| Baihetan Hydropower Station | 16,000 | — | ||
| Itaipu Dam | 14,000 | Itaipú Binacional | ||
| Xiluodu Hydropower Station | 13,860 | China Yangtze Power | ||
| Usina Hidrelétrica de Belo Monte | 11,000 | Norte Energia | ||
| Guri Hydroelectric Plant | 10,235 | EDELCA | ||
| Wudongde Dam | 10,200 | — | ||
| Jebel Ali Power and Desalination Plant | 9,547 | DEWA | ||
| Usina Hidrelétrica de Tucuruí | 8,370 | — | ||
| Kashiwazaki-Kariwa Nuclear Power Plant | 8,212 | — |
See every one of the largest plants
A free account shows the full list, and lets you search it by plant, operator or source.
Data points
Each data layer's newest points, grouped as in the map's layer panel